Monday, June 18, 2012

Renovation in progress

Proposed new master bedroom, new family room, extension of bathroom, extension of living room and ancillary works at 33 Budi 2.

Construction cost : RM120,000
Variation order (V.O) : RM30,000
Date of commencement : 27 Feb 2012
Construction period : 3 months
Date of completion : 27 May 2012
Extention of time : 4 weeks
Contractor : YM Crystal Tile Sdn Bhd

Works in progress - Day 5 (week 1) - foundation work, ground floor column, beam & slab formwork

Buat saudara2ku sekelian...dimaklumkan operasi budget hotel cum homestay untuk cuti sekolah bermula minggu depan dihentikan buat sementara (cuti sekolah dah berlalu dah....) Insyaalah operasi akan bersambung untuk cuti pertengahan tahun nanti.
Day 12 (week 2) - first floor column
Week 2 - first floor beam & slab completed
Week 2
Week 3 - roof beam & gutter completed
Week 3 - balcony cantilever slab
Week 4 - Concrete tiles roofing, brickwall completed.
Week 4 - Door and window frame
Week 4
Week 5 - cement plastering internal and external is in progress. Bathroom wall at ground floor been demolished and new wall at about 1 feet wider from the original has been constructed.
Week 5 -Wiring works is in progress.
Week 6 - door and window frame completed, cement plastering, wiring works in progress
Week 7 - plaster ceiling at new master bedroom in progress
Week 7 - plaster ceiling at car porch
Week 7 - demolished of brickwall at existing master bedroom
Week 8 - 9, installed of the aluminium window, internal plaster ceiling
Week - 9
Week 9, brickwall fencing
Week 9, demolished of existing steel fencing, balcony side wall in progress
 Week 16, completion of wrought iron gate.
Week 16
Week 16
Week 16, 97% work done